Seven summits to climb when developing condos in San Diego

September 22, 2014

I have 35 new rental projects in my downtown San Diego database. In addition, I also have a small list of projects that are supposed to be condominiums, but there does not seem to be any dirt being moved for those projects.
Vertical condominiums are scary things to develop. Here’s why:
First, the typical vertical condominium takes 24 months to process, including creating the working drawings and getting them through the permit process. Then it takes two years to build.
Therefore, developers have to convince themselves that the market will be there in four years. After all, you cannot close escrow on one unit until all the units are built and you have a certificate of occupancy.
Second, you have to determine four years in advance exactly what the market will want at the time the units are ready for occupancy. Condominium markets have changing tastes as many a developer has found out. What unit mix should you lock in?
The big problem with planning vertical condominiums is that once you have made a decision on unit mix and sizes, you are pretty well locked in for the duration.
Third, the costs of construction are in motion. A developer applies for a loan to acquire the land and construct the project, but no general contractor is going to lock in pricing that far in advance. In today’s world, the price of materials is not exactly stable and the price of labor is creeping up.
Fourth, from day one, prices have to be established. You can’t get a loan without knowing what the product will sell for. And that means you have to project years in advance what the state of the market will be at the time of project completion.
Fifth, it is necessary to determine what interest rates will be in four years, as well as during the period of the construction loan. What would be the effect on projected sales and pricing if interest went from their current level to maybe six or seven percent?
Sixth, developers are inevitably faced with an absence of knowledge about their competition. There is a herd mentality in the industry. In the last round, there were 50-plus condominium projects built downtown in a seven-year time-frame (plus a half-dozen condominium conversions). Most of the developers made money or at least came out alive. Those who came in early in the game did particularly well.
Now, we are in a strange time. No one has broken ground on a new condominium project in downtown San Diego in almost a decade and it will be at least three years before the next one is complete (unless some of the rental projects under or near construction sells to a condominium developer).
Fortunately, in the 2000 to 2007 time frame, the market was steaming; loans were ridiculously easy to obtain (including liar loans); and the national economy was buoyant. Then the economy started to unravel.
Also, fortunately, we did not have a major overhang of unsold units. In Miami, there were 30,000 high-rise condominium units under construction or completed and unsold when the wheels came off the economy.
And seventh, and finally, the developer must roll the dice on what the national and local economy will be doing in four years. What will the job market look like? How about inflation? Will we be engaged in warlike activities somewhere in the globe?
What is it like for a developer who is building a 200-unit high-rise to have the market go sideways after the building is complete and only half the units are sold?
Such is the life of a vertical condominium developer.
P.S. And then there is also the specter of litigation. Of the 57 projects built downtown from 2000 to 2007, 42 were subject to litigation. No laughing matter.
Nevin is a team leader in market research and forensic services at Xpera Group, the West Coast’s largest source of experts in construction and real estate. He can be reached at anevin@xperagroup.com.
Written by Alan Nevin via The Daily Transcript

Livibility scores in Tierrasanta, CA 92124

September 22, 2014

Great resource for livibility in Tierrasanta.
Please click below:
http://www.areavibes.com/san+diego-ca/tierrasanta/livability/

San Diego’s Economy is Experiencing a Strong Return- One Report; UCLA: SD economy firing on all Cylinders

September 22, 2014

216 Million for San Ysidro Expansion Approved by House

September 22, 2014

The San Diego Regional Chamber of Commerce welcomed passage Wednesday of a House appropriations bill that includes $216 million for the final phase of a project to modernize and expand the San Ysidro Port of Entry.

“Business and community leaders are unified in prioritizing this project as it strengthens our competitive viability on a global scale,” said Jerry Sanders, president and CEO of the chamber. “The San Diego economy will benefit from this project with billions of dollars in revenue and tens of thousands of jobs.”

The bill must still pass the Senate, and the White House has expressed concern about aspects of the legislation unrelated to San Ysidro, but the chamber said it is committed to “continuing our efforts in advocating for this funding” as the legislation proceeds through Congress.

“I am proud to be part of the bipartisan San Diego delegation that made the San Ysidro Port of Entry Modernization and Expansion Project a top priority,” said Rep. Juan Vargas. whose 51st District includes the border area. “Although I greatly disagree with many of the provisions within the bill, I’m pleased that its approval on the House floor brings us one step closer to fully funding this project.”

Early this year, at the urging of the San Diego delegation, Congress approved $226 million for the third phase of the project. The funding approved by the House on Wednesday is for completion of this long-awaited project.

The San Ysidro Land Port of Entry, the world’s busiest land port, serves more than 50,000 vehicles and approximately 25,000 pedestrian crossings every day. In a 2007 study, the San Diego Association of Governments estimated that delays due to border wait times cost $7.2 billion in lost output and more than 62,000 jobs. In 2011, the United States and Mexico agreed to modernize and expand the San Ysidro Land Port of Entry.
Written by CHRIS JENNEWEIN vie Times of SD

Bright Horizons Child Care in Tierrasanta, CA 92124

September 22, 2014

Need information regarding Child care in Tierrasanta?
Please click below:
http://child-care-preschool.brighthorizons.com/ca/sandiego/tierrasanta

Weather for Tierrasanta, CA 92124

September 22, 2014

Want to know what the days weather will bring in Tierrasanta?
Please click below:
http://www.wunderground.com/weather-forecast/US/CA/Tierrasanta.html

Tierrasanta Elementary

September 22, 2014

Need information about Tierrasanta Elementary?
Please click below:
http://www.sandi.net/tierrasanta